Photo report from the construction site of the SYMBOL residential complex for July 2023 from the Credo company:
The floor slab of the 6th floor was concreted
The vertical structures of the 7th floor were completed
The floor slab of the 7th floor was concreted
We continue brickwork of external and internal walls of 2-4 floors
We have installed ventilation units from 1-5 floors